Dryout design considerations for cryogenic gas plants: Part 1

A well-conducted cold plant dryout will help plant commissioning and ensure start-up goes smoothly and does not last any longer than necessary

Scott A Miller, David A Jelf, J A Anguiano and Joe T Lynch Honeywell UOP

A cryogenic plant dryout is a critical step during start-up, but it often does not receive proper atten- tion early in the project that would allow successful execution. For this discussion, ‘cold plant’ refers to a cry- ogenic turboexpander plant for natural gas liquids (NGLs) recovery, which recovers liquids comprised of either ethane and heavier components (often referred to as C₂+ liquids or NGLs) or propane and heavier components (often referred to as C₃+ liquids or liquefied petroleum gas [LPG]). A cold plant dryout can be executed correctly the first time. The owner/operator can be confident that the cold plant is dry prior to cooling down when proper design features are implemented, and guidelines are followed. All gas processors know that water must be removed from the cold plant. However, knowing the best method for remov- ing water; how much water has been removed during the dryout period; and when dryout is complete, can be chal- lenging. Far too often, a dryout is stopped before the cold plant is completely dry. Hydrate problems The solid that forms when water is present in a hydrocar- bon stream is not ‘ice’, but a crystalline structure known as a hydrate. Hydrates can form at conditions where solids would not be expected and will form above the freezing point of water. They are a physical combination of water and other chemical constituents, like those found in natural gas processing, which have an ‘ice-like’ appearance. 1 Hydrates form when enough water is present at the right combination of temperature and pressure and tend to favour systems with low temperature and high pressure. 2 For gas plant owners/operators, this means that when the plant begins to cool down, hydrates will form in process areas where sufficient water is present, restricting or com - pletely obstructing process flow. It is not uncommon to see hydrates obstructing flow through heat exchanger passes or the strainers that pro- tect the heat exchanger from construction dirt and debris. Hydrates can cause enough pressure drop to rip apart strainers, allowing dirt and debris to enter and damage the downstream heat exchanger. In the case of thermosyphon reboilers and side heaters, hydrate formation may restrict the flow through the exchanger and reduce the amount of

heat input to the column enough to prevent achieving the bottoms liquid product purity specification. Hydrates may also form on the cold plant fractiona- tion column trays and packing. The result is a decrease in efficiency, causing low product recovery and potentially off-specification liquid product. Hydrates are also known to plug control valves and plant instrumentation. Water can enter the plant equipment through rain or con- densation from open piping during construction and through water left after hydrostatic testing. The single most impor- tant step that can be taken prior to the start-up of a cold process plant is to drain and blow out as much free water as possible from the piping and equipment. Eventually, all the water must be removed from the cold plant to the parts per million (ppm) level for the cold plant to operate safely and efficiently. Not all of the water can be removed simply by draining low points. The remaining water must be removed by a combination of moving the water to a low point where it can be drained and absorbing the water in a vapour stream so it can be removed from the cold plant equipment and pip- ing. Several options for eliminating this remaining water are presented in the next section. Dryout options The following options are common approaches to drying out a cold plant prior to cooldown. A description of each option is given, discussing its advantages and disadvan- tages, in order from the least cost-effective to the most cost-effective option. Option 1 involves pressure cycling with nitrogen. In this approach, sections of the cold plant are isolated to be pres- surised and depressurised multiple times using nitrogen. This method requires no piping design considerations other than properly locating low-point drains and ensuring the drains are of sufficient number and size to remove water from the system. This dryout approach requires a large quantity of nitro- gen to be available and can be very expensive because of the amount of nitrogen consumed. This dryout option is less likely to be successful if large quantities of free water (puddles of water) are still present in the system. It is more difficult to determine the amount of water remaining in the cold plant after nitrogen purging and whether all water has

5

Gas 2024

www.digitalrefining.com

Powered by